πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

ONSHORE WIND Β· WEST

Onshore wind project 243, Bonneville County

Onshore wind project 243, Bonneville County is a 64.8 MW onshore wind request withdrawn in the West interconnection queue, in Bonneville County, Idaho, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
243
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Ridgeline Alternative Energy, LLC
Connection point (POI)
Line to existing Wolverine Creek Goshen substation phase II
Location
Bonneville County, Idaho
Technology
Wind: 64.8 MW
Total requested
64.8 MW
Service type
Network resource (NRIS)
Study phase
Rolled to Q0029-b
Queue status
Withdrawn
Entered queue
6 November 2008
Proposed online date
November 2009

Location

Marker shows the centre of Bonneville County; the queue data does not give exact sites.

Power plants in Idaho Β· Transmission lines in Idaho

Other requests in Bonneville County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem