BATTERY STORAGE · NYISO

Wallkill Energy Storage

Wallkill Energy Storage is a 100 MW battery storage request withdrawn in the NYISO interconnection queue, in Ulster County, New York, connecting to CHG&E.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1491
Grid region
NYISO (New York)
Utility / transmission owner
CHG&E
Developer
ACE DevCo NC, LLC
Connection point (POI)
Ohioville 115 kV Substation Bus 2
Location
Ulster County, New York
Technology
Battery: 100 MW
Total requested
100 MW
Queue status
Withdrawn
Entered queue
22 December 2022

Location

Marker shows the centre of Ulster County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Ulster County