Solar project 120, Greenwood County

Solar project 120, Greenwood County is a 75.0 MW solar request withdrawn in the Southeast interconnection queue, in Greenwood County, South Carolina, connecting to Santee Cooper.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
120
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Santee Cooper
Location
Greenwood County, South Carolina
Technology
Solar: 75.0 MW
Total requested
75.0 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
14 December 2018
Proposed online date
December 2021

Location

Marker shows the centre of Greenwood County; the queue data does not give exact sites.

Power plants in South Carolina Β· Transmission lines in South Carolina

Other requests in Greenwood County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem