United States › Grid › Interconnection queues › Maine

ONSHORE WIND · ISO-NE

Wind Increase (see Q452)

Wind Increase (see Q452) is a 0.8 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Somerset County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2014 (completed)
  2. Withdrawn / abandonedJun 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
454
Grid region
ISO-NE (New England)
Connection point (POI)
Harris substation near the Town of Jackman and Misery Township Somerset County, Maine
Location
Somerset County, Maine
Technology
Wind: 0.8 MW
Total requested
0.8 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
7 April 2014
Proposed online date
December 2018
Withdrawn
June 2016

Location

Marker shows the centre of Somerset County; the queue data does not give exact sites.

Power plants in Maine · Transmission lines in Maine

Other requests in Somerset County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem