United States βΊ Grid βΊ Interconnection queues βΊ Texas
ONSHORE WIND Β· ERCOTYoung Wind II
Young Wind II is a 152 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Young County, Texas.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedNov 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 23INR0493
- Grid region
- ERCOT (Texas)
- Developer
- Young Wind II
- Connection point (POI)
- Thomas Price
- Location
- Young County, Texas
- Technology
- Wind: 152 MW
- Total requested
- 152 MW
- Study phase
- FIS & SS Incomplete
- Queue status
- Withdrawn
- Proposed online date
- December 2023
- Withdrawn
- November 2022
Location
Marker shows the centre of Young County; the queue data does not give exact sites.
Other requests in Young County
- Olney AGR1Other Β· 10.0 MW Β· agreement signed
- Trinity Hills Wind repowerOnshore wind Β· -27.0 MW Β· agreement signed
- Miller Bend Energy BESSSolar + storage Β· 548 MW Β· in study
- Miller Bend Energy SolarSolar + storage Β· 532 MW Β· in study
- Sweetheart BESSSolar + storage Β· 310 MW Β· in study
- Tapaderos SolarSolar + storage Β· 302 MW Β· in study
- Sweetheart SolarSolar + storage Β· 301 MW Β· in study
- Jolly Rock Storage CenterBattery storage Β· 209 MW Β· in study
- Tapaderos StorageSolar + storage Β· 207 MW Β· in study
- Red Top Solar ISolar Β· 201 MW Β· in study
- Thunderbird Valley StorageBattery storage Β· 150 MW Β· in study
- Carolina Storage Young CountyBattery storage Β· 105 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem