πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· SPP

Solar project GEN-2017-079, Castro County

Solar project GEN-2017-079, Castro County is a 49.9 MW solar request withdrawn in the SPP interconnection queue, in Castro County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedNov 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-079
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Hart Industrial 115kV sub
Location
Castro County, Texas
Technology
Solar: 49.9 MW
Total requested
49.9 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 May 2017
Proposed online date
March 2023
Withdrawn
November 2020

Location

Marker shows the centre of Castro County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Castro County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem