West Springs Wind Farm

West Springs Wind Farm is a 158 MW onshore wind request withdrawn in the CAISO interconnection queue, in Riverside County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedMar 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1299
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
El Casco 230 kV
Location
Riverside County, California
Technology
Wind: 158 MW
Total requested
158 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
2 May 2016
Proposed online date
February 2021
Withdrawn
March 2018

Location

Marker shows the centre of Riverside County; the queue data does not give exact sites.