Solar project AB2-159, Burlington County

Solar project AB2-159, Burlington County is a 1.3 MW solar request withdrawn in the PJM interconnection queue, in Burlington County, New Jersey, connecting to PSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2016 (completed)
  2. Withdrawn / abandonedDec 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AB2-159
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Lumberton 13kV
Location
Burlington County, New Jersey
Technology
Solar: 1.3 MW
Total requested
1.3 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
29 April 2016
Proposed online date
October 2016
Withdrawn
December 2017

Location

Marker shows the centre of Burlington County; the queue data does not give exact sites.