πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project H020, Webster County

Onshore wind project H020, Webster County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Webster County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2008 (completed)
  2. Withdrawn / abandonedAug 2012 (project stopped here)
  3. ConsentedAug 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H020
Grid region
MISO (Midcontinent)
Connection point (POI)
Boone Substation
Location
Webster County, Iowa
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
30 April 2008
Agreement signed
23 August 2012
Proposed online date
December 2010
Withdrawn
August 2012

Location

Marker shows the centre of Webster County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Webster County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem