ONSHORE WIND Β· MISO

Onshore wind project J3808, Webster County

Onshore wind project J3808, Webster County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Webster County, Iowa, connecting to MIDAMERICAN ENERGY CO..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedSep 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3808
Grid region
MISO (Midcontinent)
Utility / transmission owner
MIDAMERICAN ENERGY CO.
Connection point (POI)
IRVINGTON - WEBSTER 345.0kV
Location
Webster County, Iowa
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
16 April 2024
Proposed online date
May 2028
Withdrawn
September 2025

Location

Marker shows the centre of Webster County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Webster County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem