Onshore wind project R42, Webster County

Onshore wind project R42, Webster County is a 250 MW onshore wind request built and operating in the MISO interconnection queue, in Webster County, Iowa.

Queue statusOperating
  1. PlanningQueued Jul 2007 (completed)
  2. ConsentedMay 2015 (completed)
  3. Construction (completed)
  4. OperatingDec 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
R42
Grid region
MISO (Midcontinent)
Connection point (POI)
Lehigh 345 kV Substation
Location
Webster County, Iowa
Technology
Wind: 250 MW
Total requested
250 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
17 July 2007
Agreement signed
4 May 2015
Proposed online date
December 2008
Came online
December 2008

Location

Marker shows the centre of Webster County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Webster County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem