United States βΊ Grid βΊ Interconnection queues βΊ Texas
OTHER Β· ERCOTGoldeneye II BESS
Goldeneye II BESS is a 101 MW other request withdrawn in the ERCOT interconnection queue, in Bell County, Texas.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedAug 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 25INR0158
- Grid region
- ERCOT (Texas)
- Developer
- BLACK MOUNTAIN ENERGY STORAGE II
- Connection point (POI)
- 3423 KILLEEN SS
- Location
- Bell County, Texas
- Technology
- Other: 101 MW
- Total requested
- 101 MW
- Study phase
- FIS & SS Incomplete
- Queue status
- Withdrawn
- Proposed online date
- April 2025
- Withdrawn
- August 2022
Location
Marker shows the centre of Bell County; the queue data does not give exact sites.
Other requests in Bell County
- Chillingham SolarSolar Β· 352 MW Β· agreement signed
- Limewood SolarSolar + storage Β· 205 MW Β· agreement signed
- Goldeneye BESSBattery storage Β· 202 MW Β· agreement signed
- Cosper SolarSolar Β· 148 MW Β· agreement signed
- Big Elm StorageSolar + storage Β· 120 MW Β· agreement signed
- Hermes SolarSolar + storage Β· 100 MW Β· agreement signed
- Hermes StorageSolar + storage Β· 100 MW Β· agreement signed
- Limewood StorageSolar + storage Β· 50.0 MW Β· agreement signed
- Riviera GasGas Β· 942 MW Β· in study
- Lavita BESSBattery storage Β· 606 MW Β· in study
- Bell County Morgan StorageBattery storage Β· 256 MW Β· in study
- GridGuardian BESSBattery storage Β· 228 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem