United States › Grid › Interconnection queues › West Virginia

BATTERY STORAGE · PJM

New Creek Mountain Energy Storage

New Creek Mountain Energy Storage is a 32.0 MW battery storage request withdrawn in the PJM interconnection queue, in Grant County, West Virginia, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2010 (completed)
  2. Withdrawn / abandonedNov 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2016 (not reached)
  6. Closed (not reached)

Request details

Queue ID
W4-037
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Bismark 500kV
Location
Grant County, West Virginia
Technology
Battery: 32.0 MW
Total requested
32.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
30 December 2010
Proposed online date
December 2018
Came online
December 2016
Withdrawn
November 2018

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.

Power plants in West Virginia · Transmission lines in West Virginia