ONSHORE WIND Β· PJMOnshore wind project W3-021A, Crawford County
Onshore wind project W3-021A, Crawford County is a 70.0 MW onshore wind request withdrawn in the PJM interconnection queue, in Crawford County, Pennsylvania, connecting to PENELEC.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2010 (completed)
- Withdrawn / abandonedOct 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- W3-021A
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PENELEC
- Connection point (POI)
- Corry East 115kV
- Location
- Crawford County, Pennsylvania
- Technology
- Wind: 70.0 MW
- Total requested
- 70.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 23 August 2010
- Proposed online date
- December 2014
- Withdrawn
- October 2012
Location
Marker shows the centre of Crawford County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Crawford County
- Franklin SolarSolar Β· 20.0 MW Β· agreement signed
- Nichols SolarSolar Β· 20.0 MW Β· agreement signed
- Henry SolarSolar Β· 20.0 MW Β· agreement signed
- Welcome Solar IISolar + storage Β· 19.9 MW Β· agreement signed
- Welcome Solar III, LLCSolar + storage Β· 17.9 MW Β· agreement signed
- Solar project AG2-176, Crawford CountySolar Β· 150 MW Β· in study
- Battery storage project AH2-420, Crawford CountyBattery storage Β· 50.0 MW Β· in study
- Solar project AH2-119, Crawford CountySolar Β· 15.0 MW Β· in study
- Solar project AH2-095, Crawford CountySolar Β· 3.3 MW Β· in study
- Solar project AI1-160, Crawford CountySolar Β· 1.4 MW Β· in study
- Shorebird SolarSolar Β· 117 MW Β· suspended
- Morgan Street-Cochranton 34.5 kVSolar Β· 15.0 MW Β· suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem