United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
GAS Β· PJMGas project AD1-127, Cambria County
Gas project AD1-127, Cambria County is a 235 MW gas request withdrawn in the PJM interconnection queue, in Cambria County, Pennsylvania, connecting to PENELEC.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2017 (completed)
- Withdrawn / abandonedMay 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AD1-127
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PENELEC
- Connection point (POI)
- Cambria Slope 115 kV
- Location
- Cambria County, Pennsylvania
- Technology
- Gas: 235 MW
- Total requested
- 235 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 28 September 2017
- Proposed online date
- September 2020
- Withdrawn
- May 2018
Location
Marker shows the centre of Cambria County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Cambria County
- Solar + storage project AI2-446, Cambria CountySolar + storage Β· 150 MW Β· in study
- Battery storage project AJ1-016, Cambria CountyBattery storage Β· 100 MW Β· in study
- Solar + storage project AI1-179, Cambria CountySolar + storage Β· 100 MW Β· in study
- Solar project AH2-116, Cambria CountySolar Β· 85.0 MW Β· in study
- Onshore wind project AH2-247, Cambria CountyOnshore wind Β· 83.3 MW Β· in study
- Onshore wind project AH2-248, Cambria CountyOnshore wind Β· 83.3 MW Β· in study
- Onshore wind project AH2-403, Cambria CountyOnshore wind Β· 83.3 MW Β· in study
- Onshore wind project AH2-292, Cambria CountyOnshore wind Β· 77.0 MW Β· in study
- Maple Hill-Fiddlers 1 SP (Bear Rock)Solar Β· 50.0 MW Β· in study
- Solar project AH2-320, Cambria CountySolar Β· 10.0 MW Β· in study
- Solar + storage project AI1-114, Cambria CountySolar + storage Β· 9.9 MW Β· in study
- CPV Fairview Energy CenterGas Β· 1,050 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem