NUCLEAR · PJM

Clavert Cliffs 1 and 2

Clavert Cliffs 1 and 2 is a 63.0 MW nuclear request built and operating in the PJM interconnection queue, in Calvert County, Maryland, connecting to BGE.

Queue statusOperating
  1. PlanningQueued Feb 2004 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2005 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
M04
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
BGE
Connection point (POI)
Calvert Cliffs
Location
Calvert County, Maryland
Technology
Nuclear: 63.0 MW
Total requested
63.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
25 February 2004
Proposed online date
June 2005
Came online
June 2005

Location

Marker shows the centre of Calvert County; the queue data does not give exact sites.

Power plants in Maryland · Transmission lines in Maryland

Other requests in Calvert County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem