United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTEiffel Solar
Eiffel Solar is a 241 MW solar request built and operating in the ERCOT interconnection queue, in Lamar County, Texas.
Request details
- Queue ID
- 22INR0223
- Grid region
- ERCOT (Texas)
- Developer
- Paris Farm Solar, LLC
- Connection point (POI)
- POI changed to Double Tap 138kV 1693 Paris SW - 11770 Lamar Blossom Tap and 1693 Paris SW - 1768 Deport Rea
- Location
- Lamar County, Texas
- Technology
- Solar: 241 MW
- Total requested
- 241 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 10 July 2019
- Agreement signed
- 19 March 2021
- Proposed online date
- October 2023
- Came online
- November 2023
Location
Marker shows the centre of Lamar County; the queue data does not give exact sites.
Other requests in Lamar County
- Baker Branch SolarSolar Β· 469 MW Β· agreement signed
- Bug Tussle Wind ProjectOnshore wind Β· 397 MW Β· agreement signed
- Rowdy Creek SolarSolar + storage Β· 352 MW Β· agreement signed
- Delilah Solar 2Solar Β· 318 MW Β· agreement signed
- Delilah Solar 1Solar Β· 300 MW Β· agreement signed
- Samson Solar 3Solar Β· 250 MW Β· agreement signed
- Samson Solar 1Solar Β· 250 MW Β· agreement signed
- Star Dairy StorageSolar + storage Β· 205 MW Β· agreement signed
- Samson Solar 2Solar Β· 203 MW Β· agreement signed
- Echols Grove, LLCSolar Β· 201 MW Β· agreement signed
- Rowdy Creek BESSSolar + storage Β· 176 MW Β· agreement signed
- MRG Goody SolarSolar + storage Β· 171 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem