🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR · CAISO

Centinela Solar Energy Facility 2MWFT

Centinela Solar Energy Facility 2MWFT is a 2.0 MW solar request withdrawn in the CAISO interconnection queue, in Imperial County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2014 (completed)
  2. Withdrawn / abandonedSep 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1090
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Imperial Valley 230kV sub
Location
Imperial County, California
Technology
Solar: 2.0 MW
Total requested
2.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
11 June 2014
Proposed online date
January 2015
Withdrawn
September 2014

Location

Marker shows the centre of Imperial County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Imperial County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem