🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Montana

ONSHORE WIND · WEST

Onshore wind project 343, Wheatland County

Onshore wind project 343, Wheatland County is a 11.3 MW onshore wind request built and operating in the West interconnection queue, in Wheatland County, Montana, connecting to NorthWestern Energy.

Queue statusOperating
  1. PlanningQueued Jun 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
343
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Two Dot Wind Substation
Location
Wheatland County, Montana
Technology
Wind: 11.3 MW
Total requested
11.3 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
8 June 2018
Proposed online date
December 2018
Came online
December 2018

Location

Marker shows the centre of Wheatland County; the queue data does not give exact sites.

Power plants in Montana · Transmission lines in Montana

Other requests in Wheatland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem