United States β€Ί Grid β€Ί Interconnection queues β€Ί California

GAS Β· CAISO

Apg Wilson Station

Apg Wilson Station is a 525 MW gas request withdrawn in the CAISO interconnection queue, in Merced County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2008 (completed)
  2. Withdrawn / abandonedNov 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
341
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Wilson Substation 230kV Bus
Location
Merced County, California
Technology
Gas: 525 MW
Total requested
525 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
23 April 2008
Proposed online date
March 2012
Withdrawn
November 2008

Location

Marker shows the centre of Merced County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Merced County