United States β€Ί Grid β€Ί Interconnection queues β€Ί Alabama

HYDRO Β· SOUTHEAST

Hydro project IC-319, Marengo County

Hydro project IC-319, Marengo County is a 48.0 MW hydro request withdrawn in the Southeast interconnection queue, in Marengo County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2013 (completed)
  2. Withdrawn / abandonedOct 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-319
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Bellamy - Demopolis 115 kV Line
Location
Marengo County, Alabama
Technology
Hydro: 48.0 MW
Total requested
48.0 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
17 October 2013
Withdrawn
October 2013

Location

Marker shows the centre of Marengo County; the queue data does not give exact sites.

Power plants in Alabama Β· Transmission lines in Alabama

Other requests in Marengo County