Solar project C3-191, Umatilla County is a 300 MW solar request withdrawn in the West interconnection queue, in Umatilla County, Oregon, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C3-191
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Capstone substation
Location
Umatilla County, Oregon
Technology
Solar: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
15 May 2023
Proposed online date
May 2028

Location

Marker shows the centre of Umatilla County; the queue data does not give exact sites.

Power plants in Oregon Β· Transmission lines in Oregon

Other requests in Umatilla County