πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

OTHER Β· CAISO

Merced Power

Merced Power is a 0.5 MW other request built and operating in the CAISO interconnection queue, in Merced County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Mar 2014 (completed)
  2. ConsentedJul 2014 (completed)
  3. Construction (completed)
  4. OperatingJul 2014 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1005
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Merced #1 70kV Line
Location
Merced County, California
Technology
Other: 0.5 MW
Total requested
0.5 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Operational
Entered queue
11 March 2014
Agreement signed
29 July 2014
Proposed online date
April 2014
Came online
July 2014

Location

Marker shows the centre of Merced County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Merced County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem