ONSHORE WIND Β· SPP

Onshore wind project GEN-2023-GR6, Caddo County

Onshore wind project GEN-2023-GR6, Caddo County is a 74.3 MW onshore wind request withdrawn in the SPP interconnection queue, in Caddo County, Oklahoma, connecting to WFEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2023 (completed)
  2. Withdrawn / abandonedAug 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2024 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2023-GR6
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WFEC
Connection point (POI)
Washita 138kV
Location
Caddo County, Oklahoma
Technology
Wind: 74.3 MW
Total requested
74.3 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
14 July 2023
Proposed online date
December 2024
Came online
December 2024
Withdrawn
August 2024

Location

Marker shows the centre of Caddo County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Caddo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem