SOLAR Β· ISO-NE

Solar

Solar is a 72.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Somerset County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedSep 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1125
Grid region
ISO-NE (New England)
Connection point (POI)
44°36'30.65"N 69°38'23.26"W. CMP Line 241, new substation on 115kV line between Heywood Road Substation and County Road Substation.
Location
Somerset County, Maine
Technology
Solar: 72.0 MW
Total requested
72.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
21 April 2021
Proposed online date
January 2024
Withdrawn
September 2023

Location

Marker shows the centre of Somerset County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Somerset County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem