Potrero Hills Energy

Potrero Hills Energy is a 9.6 MW other request withdrawn in the CAISO interconnection queue, in Solano County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2010 (completed)
  2. Withdrawn / abandonedNov 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
575
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Brighton-Davis 115 kV Line
Location
Solano County, California
Technology
Other: 9.6 MW
Total requested
9.6 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 February 2010
Proposed online date
June 2013
Withdrawn
November 2010

Location

Marker shows the centre of Solano County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Solano County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem