πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Royal Solar

Royal Solar is a 103 MW solar request withdrawn in the CAISO interconnection queue, in Stanislaus County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedMar 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1281
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Rio Oso - Woodland #1 115 kV line
Location
Stanislaus County, California
Technology
Solar: 103 MW
Total requested
103 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
2 May 2016
Proposed online date
December 2020
Withdrawn
March 2017

Location

Marker shows the centre of Stanislaus County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Stanislaus County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem