United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

SOLAR Β· WEST

Solar project Q152, Yuma County

Solar project Q152, Yuma County is a 20.0 MW solar request withdrawn in the West interconnection queue, in Yuma County, Arizona, connecting to Arizona Public Service.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2010 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q152
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
12/69 kV at Mittry substation
Location
Yuma County, Arizona
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
25 June 2010
Proposed online date
February 2012

Location

Marker shows the centre of Yuma County; the queue data does not give exact sites.

Power plants in Arizona Β· Transmission lines in Arizona

Other requests in Yuma County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem