United States βΊ Grid βΊ Interconnection queues βΊ New York
OTHER Β· NYISOChautauqua County Landfill
Chautauqua County Landfill is a 3.2 MW other request built and operating in the NYISO interconnection queue, connecting to NM-NG.
Request details
- Queue ID
- 353
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Chautauqua County
- Connection point (POI)
- Hartfield South Dow 34.5kV
- Location
- New York
- Technology
- Other: 3.2 MW
- Total requested
- 3.2 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 26 April 2010
Location
Marker shows the centre of County; the queue data does not give exact sites.
Other requests in County
- South Ripley Solar and BESSSolar + storage Β· 270 MW Β· in study
- Lighthouse Energy StorageBattery storage Β· 250 MW Β· in study
- Basecamp BESSBattery storage Β· 170 MW Β· in study
- York Run SolarSolar Β· 90.0 MW Β· in study
- Dewdrop WindOnshore wind Β· 62.0 MW Β· in study
- Buttercup WindOnshore wind Β· 49.9 MW Β· in study
- Goldenrod WindOnshore wind Β· 39.0 MW Β· in study
- Cassadaga WindOnshore wind Β· 127 MW Β· built
- Cassadaga WindOnshore wind Β· 127 MW Β· built
- Ball Hill WindOnshore wind Β· 103 MW Β· built
- Ball Hill WindOnshore wind Β· 103 MW Β· built
- Arkwright SummitOnshore wind Β· 78.4 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem