GAS · ISO-NEKleen Energy Project
Kleen Energy Project is a 620 MW gas request built and operating in the ISO-NE interconnection queue, in Middlesex County, Connecticut.
Request details
- Queue ID
- 95
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Sectionalize 353 Line
- Location
- Middlesex County, Connecticut
- Technology
- Gas: 620 MW · Oil
- Total requested
- 620 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 21 November 2001
- Proposed online date
- July 2011
Location
No county location in the queue data.
Power plants in Connecticut · Transmission lines in Connecticut
Other requests in Middlesex County
- Utc - P&WaGas · 7.5 MW · built
- Simple Cycle Combustion Turbine Repowering (alternative to Q647)Gas · 378 MW · withdrawn
- Gas Turbine RepoweringGas · 378 MW · withdrawn
- Battery StorageBattery storage · 305 MW · withdrawn
- Battery StorageBattery storage · 289 MW · withdrawn
- Battery Storage AdditionBattery storage · 284 MW · withdrawn
- Gas TurbineGas · 82.2 MW · withdrawn
- Battery StorageBattery storage · 80.9 MW · withdrawn
- Gas turbine repowering (Alt. to Q647)Gas · 23.0 MW · withdrawn
- Gas turbine repoweringGas · 23.0 MW · withdrawn
- EE CT DER Group StudyBattery storage · 20.0 MW · withdrawn
- Battery StorageBattery storage · 10.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem