🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Connecticut

GAS · ISO-NE

Kleen Energy Project

Kleen Energy Project is a 620 MW gas request built and operating in the ISO-NE interconnection queue, in Middlesex County, Connecticut.

Queue statusOperating
  1. PlanningQueued Nov 2001 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Jul 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
95
Grid region
ISO-NE (New England)
Connection point (POI)
Sectionalize 353 Line
Location
Middlesex County, Connecticut
Technology
Gas: 620 MW · Oil
Total requested
620 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
21 November 2001
Proposed online date
July 2011

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in Middlesex County