SOLAR Β· ERCOT

Cachena Solar 2 SLF

Cachena Solar 2 SLF is a 160 MW solar request withdrawn in the ERCOT interconnection queue, in Wilson County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedOct 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0270
Grid region
ERCOT (Texas)
Developer
Clear Fork Creek Solar LLC
Connection point (POI)
Tap 345kV 5915 STP - 5133 Elm Creek ckt 1
Location
Wilson County, Texas
Technology
Solar: 160 MW
Total requested
160 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
29 March 2022
Proposed online date
June 2024
Withdrawn
October 2022

Location

Marker shows the centre of Wilson County; the queue data does not give exact sites.