United States β€Ί Grid β€Ί Interconnection queues β€Ί California

GAS Β· CAISO

Carlsbad 2

Carlsbad 2 is a 106 MW gas request built and operating in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusOperating
  1. PlanningQueued Mar 2007 (completed)
  2. ConsentedNov 2015 (completed)
  3. Construction (completed)
  4. OperatingJun 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
189
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Encina Substation 138 kV
Location
San Diego County, California
Technology
Gas: 106 MW
Total requested
106 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
30 March 2007
Agreement signed
30 November 2015
Proposed online date
May 2010
Came online
June 2019

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in San Diego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem