🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Connecticut

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 20.0 MW battery storage request withdrawn in the ISO-NE interconnection queue, in New Haven County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2021 (completed)
  2. Withdrawn / abandonedJun 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1166
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource Oxford 26N Substation
Location
New Haven County, Connecticut
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
4 October 2021
Proposed online date
September 2024
Withdrawn
June 2025

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New Haven County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem