Solar project AG2-255, Burlington County

Solar project AG2-255, Burlington County is a 4.0 MW solar request withdrawn in the PJM interconnection queue, in Burlington County, New Jersey, connecting to PSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-255
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
South Hampton 13 kV
Location
Burlington County, New Jersey
Technology
Solar: 4.0 MW
Total requested
4.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
18 March 2021
Proposed online date
March 2022
Withdrawn
December 2024

Location

Marker shows the centre of Burlington County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Burlington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem