United States βΊ Grid βΊ Interconnection queues βΊ West Virginia
SOLAR Β· PJMTri-State Solar
Tri-State Solar is a 5.0 MW solar request withdrawn in the PJM interconnection queue, in Greenbrier County, West Virginia, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2016 (completed)
- Withdrawn / abandonedJul 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AC1-012
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Rupert 34.5kV
- Location
- Greenbrier County, West Virginia
- Technology
- Solar: 5.0 MW
- Total requested
- 5.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 23 June 2016
- Proposed online date
- October 2017
- Withdrawn
- July 2018
Location
Marker shows the centre of Greenbrier County; the queue data does not give exact sites.
Power plants in West Virginia Β· Transmission lines in West Virginia
Other requests in Greenbrier County
- Beech Ridge / Field Mtn WFWind + storage Β· 186 MW Β· built
- Beech Ridge Wind FarmOnshore wind Β· 50.6 MW Β· built
- Beech Ridge Wind FarmOnshore wind Β· 5.0 MW Β· built
- Onshore wind project N02_AEP139, Greenbrier CountyOnshore wind Β· 200 MW Β· withdrawn
- West GreenbrierCoal Β· 90.0 MW Β· withdrawn
- Solar project AG1-234, Greenbrier CountySolar Β· 50.0 MW Β· withdrawn
- Trillium PV ISolar Β· 28.0 MW Β· withdrawn
- Coal project Q61, Greenbrier CountyCoal Β· 10.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem