United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
SOLAR Β· PJMSolar project AI1-029, Delaware County
Solar project AI1-029, Delaware County is a 19.8 MW solar request withdrawn in the PJM interconnection queue, in Delaware County, Pennsylvania, connecting to PECO.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2022 (completed)
- Withdrawn / abandonedMay 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AI1-029
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PECO
- Location
- Delaware County, Pennsylvania
- Technology
- Solar: 19.8 MW
- Total requested
- 19.8 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 1 April 2022
- Proposed online date
- June 2024
- Withdrawn
- May 2022
Location
Marker shows the centre of Delaware County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Delaware County
- Solar project AI1-076, Delaware CountySolar Β· 19.8 MW Β· in study
- Springfield CSG 1Solar Β· 3.9 MW Β· suspended
- Liberty (Eddy)Gas Β· 521 MW Β· built
- Phillips Island CT1, CT2, CT3, and ST4Gas Β· 67.0 MW Β· built
- Liberty ElectricGas Β· 65.5 MW Β· built
- Liberty ElectricGas Β· 35.0 MW Β· built
- Phillips Island CT1, CT2,CT3 & ST4Gas Β· 35.0 MW Β· built
- JerichoGas Β· 29.0 MW Β· built
- Kimberly ClarkOther Β· 20.0 MW Β· built
- LibertyGas Β· 20.0 MW Β· built
- Phillips Island CT1, CT2, CT3, CT4Gas Β· 10.0 MW Β· built
- Sunoil Gen UnitGas Β· 8.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem