Gas Turbine is a 185 MW gas request withdrawn in the ISO-NE interconnection queue, in New Haven County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2007 (completed)
  2. Withdrawn / abandonedNov 2007 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
223
Grid region
ISO-NE (New England)
Connection point (POI)
East Shore-Grand Ave 115 kV line
Location
New Haven County, Connecticut
Technology
Gas: 185 MW
Total requested
185 MW
Service type
Other
Queue status
Withdrawn
Entered queue
25 July 2007
Proposed online date
May 2010
Withdrawn
November 2007

Location

No county location in the queue data.