Bresh Hybrid

Bresh Hybrid is a 59.2 MW solar + storage request withdrawn in the NYISO interconnection queue, in Ulster County, New York, connecting to CHGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2024 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C24-172
Grid region
NYISO (New York)
Utility / transmission owner
CHGE
Developer
Blue Stone Renewable XVI
Connection point (POI)
BOULEVARD 69 kV SUBSTATION
Location
Ulster County, New York
Technology
Solar: 59.2 MW Β· Battery
Total requested
59.2 MW
Queue status
Withdrawn
Entered queue
17 September 2024

Location

Marker shows the centre of Ulster County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Ulster County