United States › Grid › Interconnection queues › New York

SOLAR + STORAGE · NYISO

Christmiller Solar

Christmiller Solar is a 20.0 MW solar + storage request withdrawn in the NYISO interconnection queue, in Cattaraugus County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2021 (completed)
  2. Withdrawn / abandonedDec 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1173
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Northland Power US Projects
Connection point (POI)
Dake Hill – Machias 34.5kV
Location
Cattaraugus County, New York
Technology
Solar: 20.0 MW · Battery
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
17 May 2021
Withdrawn
December 2022

Location

Marker shows the centre of Cattaraugus County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Cattaraugus County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem