United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

HYDRO Β· ISO-NE

Hydro Uprate

Hydro Uprate is a 1.0 MW hydro request withdrawn in the ISO-NE interconnection queue, in Androscoggin County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2009 (completed)
  2. Withdrawn / abandonedSep 2009 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
309
Grid region
ISO-NE (New England)
Connection point (POI)
CMP Gulf Island 115 kV
Location
Androscoggin County, Maine
Technology
Hydro: 1.0 MW
Total requested
1.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
1 September 2009
Proposed online date
December 2009
Withdrawn
September 2009

Location

Marker shows the centre of Androscoggin County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Androscoggin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem