Waterside Power - 180 MW

Waterside Power - 180 MW is a 204 MW gas request withdrawn in the ISO-NE interconnection queue, in Fairfield County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2003 (completed)
  2. Withdrawn / abandonedJul 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
104
Grid region
ISO-NE (New England)
Connection point (POI)
Waterside 115 kV
Location
Fairfield County, Connecticut
Technology
Gas: 204 MW · Oil
Total requested
204 MW
Service type
Network resource (NRIS)
Study phase
Facility Study
Queue status
Withdrawn
Entered queue
6 March 2003
Proposed online date
December 2011
Withdrawn
July 2010

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in Fairfield County