SOLAR Β· ERCOT

Tres Margaritas Solar

Tres Margaritas Solar is a 61.0 MW solar request withdrawn in the ERCOT interconnection queue, in Dimmit County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2021 (completed)
  2. Withdrawn / abandonedFeb 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0088
Grid region
ERCOT (Texas)
Developer
Gransolar Texas Six, LLC
Connection point (POI)
Tap 138kV 8613 Big Wells β€šΓ„Γ¬ 8212 Dilley Switching Station
Location
Dimmit County, Texas
Technology
Solar: 61.0 MW
Total requested
61.0 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
12 July 2021
Proposed online date
June 2026
Withdrawn
February 2025

Location

Marker shows the centre of Dimmit County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Dimmit County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem