United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

Short Tract Energy Storage

Short Tract Energy Storage is a 20.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Livingston County, New York, connecting to RG&E.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2022 (completed)
  2. Withdrawn / abandonedFeb 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1454
Grid region
NYISO (New York)
Utility / transmission owner
RG&E
Developer
Ozone Renewables
Connection point (POI)
RG&E Short Tract Road Substation
Location
Livingston County, New York
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
25 October 2022
Withdrawn
February 2023

Location

Marker shows the centre of Livingston County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Livingston County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem