Solar project 613, Deschutes County

Solar project 613, Deschutes County is a 9.9 MW solar request built and operating in the West interconnection queue, in Deschutes County, Oregon, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Aug 2014 (completed)
  2. ConsentedAug 2015 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
613
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Tumbleweed Solar LLC
Connection point (POI)
Circuit 5D184, Pronghorn, out of Deschutes substation
Location
Deschutes County, Oregon
Technology
Solar: 9.9 MW
Total requested
9.9 MW
Service type
Network resource (NRIS)
Study phase
IA signed August 17, 2015
Queue status
Operational
Entered queue
22 August 2014
Agreement signed
17 August 2015
Proposed online date
December 2017

Location

Marker shows the centre of Deschutes County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Deschutes County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem