United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

BATTERY STORAGE Β· MISO

Battery storage project J2592, Tuscola County

Battery storage project J2592, Tuscola County is a 50.0 MW battery storage request withdrawn in the MISO interconnection queue, in Tuscola County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2592
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Thetford (Atlanta) - Karn 138 kV line
Location
Tuscola County, Michigan
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
14 September 2022
Proposed online date
September 2026
Withdrawn
August 2025

Location

Marker shows the centre of Tuscola County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Tuscola County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem