Highland North

Highland North is a 73.6 MW onshore wind request built and operating in the PJM interconnection queue, in Cambria County, Pennsylvania, connecting to PENELEC.

Queue statusOperating
  1. PlanningQueued Oct 2006 (completed)
  2. ConsentedFeb 2011 (completed)
  3. Construction (completed)
  4. OperatingMar 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
R32
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Salix - Claysburg 115kV
Location
Cambria County, Pennsylvania
Technology
Wind: 73.6 MW
Total requested
73.6 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
30 October 2006
Agreement signed
8 February 2011
Proposed online date
March 2012
Came online
March 2012

Location

Marker shows the centre of Cambria County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Cambria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem