SOLAR Β· CAISO

FRV Orion Solar

FRV Orion Solar is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Merced County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2010 (completed)
  2. Withdrawn / abandonedJun 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
549
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Mercy Springs Oro Loma 70kV line
Location
Merced County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 January 2010
Proposed online date
March 2012
Withdrawn
June 2010

Location

Marker shows the centre of Merced County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Merced County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem