Onshore wind interconnection queue in the USA (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown71,187 MW
Active in queue1,187 MW7 requests
Agreement signed383 MW3 requests
Withdrawn12216.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Cattleman Wind A
Onshore wind Β· RWE Renewables Development, LLC
202 MWPaused / redesign Castro, TXERCOT Sep 2013target 2021
Cattleman Wind B
Onshore wind Β· RWE Renewables Development, LLC
202 MWPaused / redesign Castro, TXERCOT Sep 2013target 2021
Stella 2 Wind
Onshore wind Β· Eon
201 MWPaused / redesign Kenedy, TXERCOT Jun 2013target 2022
Onshore wind project GI-2013-5, Arapahoe County
Onshore wind
201 MWAgreement signed Arapahoe, COWest Jul 20132014
Tierra Blanca W
Onshore wind Β· RWE Renewables Development, LLC
200 MWPaused / redesign Randall, TXERCOT Sep 2013target 2021
Harald (BearKat Wind B)
Onshore wind Β· McCrae Wind Energy II, LLC
162 MWAgreement signed Glasscock, TXERCOT Nov 2013target 2026
Onshore wind project GI-2013-4, Jefferson County
Onshore wind
19.9 MWAgreement signed Jefferson, COWest Jun 2013target 2015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)