Onshore wind interconnection queue in the USA (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown41,288 MW
Active in queue1,288 MW4 requests
Agreement signed0.0 MW0 requests
Withdrawn28943.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 10-037, Gilliam County
Onshore wind
500 MWPaused / redesign Gilliam, ORWest Aug 2010target 2015
Onshore wind project 10-036, Sherman County
Onshore wind
400 MWPaused / redesign Sherman, ORWest Mar 2010target 2014
Onshore wind project G0435, Morrow County
Onshore wind
238 MWIn study Morrow, ORWest Aug 2010target 2013
Northdraw Wind
Onshore wind Β· National Renewable Solutions
150 MWPaused / redesign Randall, TXERCOT Jun 2010target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)