Requests shown103,547 MW
Active in queue3,547 MW10 requests
Agreement signed252 MW4 requests
Withdrawn6223.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Maidsville CCGT
Gas
1,270 MWPaused / redesign Preston, WVPJM Sep 2018target 2026
Gas project J955, Sangamon County
Gas
1,165 MWUnder construction Sangamon, ILMISO Mar 2018target 2025
Gas project JEA-Q008, Duval County
Gas
645 MWIn study Duval, FLSoutheast Feb 2018target 2030
Gas project 22
Gas
136 MWIn study FLSoutheast Aug 2018target 2019
Jackson Generation
Gas
120 MWAgreement signed Will, ILPJM Mar 2018target 2027
Ocean State Power uprate
Gas
73.2 MWAgreement signed Providence, RIISO-NE Apr 2018target 2026
R Massengale
Gas
58.0 MWPaused / redesign Lubbock, TXERCOT Sep 2018target 2021
Glen Falls Facility
Gas
45.0 MWAgreement signed Harrison, WVPJM Mar 2018target 2029
Brandon
Gas
21.0 MWPaused / redesign Lubbock, TXERCOT Sep 2018target 2021
Air Products GCA
Gas Β· Air Products
14.0 MWAgreement signed Galveston, TXERCOT Jun 2018target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)